City of Waukegan - Position Paper on Waukegan Harbor
The City Council has spoken with one voice on
On September 4, 2007 U.S. EPA's consultant expressed serious concerns that the harbor dredging project,[5] as it was being designed, may not result in meeting U.S. EPA's cleanup objective for the harbor. The draft Dredge Monitoring and Field Sampling Plan (essentially the preliminary design for the dredge project) released to the City by U.S. EPA on October 10, 2007 expresses a similar concern. The issue is that while dredging, PCBs will fall out of the dredging bucket and land back on the bottom of the harbor. This is a very well documented issue with mechanical dredging. There is a very strong likelihood that those "resettled" PCBs will prevent U.S. EPA from achieving their stated cleanup objective for the entire harbor.
In the preliminary
design released to the City on October 10, 2007, CH2M Hill, U.S. EPA's design
engineer, suggests that, after the dredging has been completed, additional
clean sand (up to 2 feet thick) can be placed on top of the "resettled" PCBs in
order to dilute their concentration and thus achieve the cleanup
objective. "Armoring" the bottom to
prevent big ship prop wash from disturbing or mobilizing these residual PCBs
has also been suggested as a possible solution. These both sound a lot like placing a cover over, or capping, the PCBs.
Particularly
striking in the just released preliminary design is that the project, as
currently designed, is just barely capable of meeting the cleanup objective for
the harbor. U.S. EPA's design engineer used mathematical calculations and not actual
field evidence to show how, based on the current data, it is theoretically
possible to just barely meet the cleanup objective, provided everything goes
exactly as planned and predicted. There
is virtually no margin for error or allowance for a change in conditions once
the dredging gets underway. If PCB concentrations
are higher than anticipated, the thickness of residual PCBs is more than
predicted, subsequent big ship prop wash mixes the bottom sediments after
dredging in an unpredicted way, or any other factor somehow does not go our
way, there is a very good chance that the harbor will not meet U.S. EPA's
cleanup objective.
Lastly, this is
not a new issue. The City has repeatedly
expressed these very concerns to the U.S. EPA. The City's concerns are now documented by U.S.
EPA's design engineer in the preliminary design.
Not meeting the cleanup objective means the harbor would not be "delisted" as an Area of Concern. The only reason the City is participating in the $39 million + dredging project is to "delist" the harbor. This would be the worst possible outcome for the City. After spending nearly $14 million of the taxpayers' money the City would be left with a deep industrial harbor that remains listed as an Area of Concern.
Since 2004,
when the City Council rejected the Yeoman Creek Landfill option, the City has
expressed concern that the dredging project is too expensive and may not
achieve U.S. EPA's cleanup objective. The City suggested an alternative approach: place an engineered cap over the contaminated
sediments on the bottom of the harbor.[6] Placing an engineered cap over the sediments would
be much less expensive than U.S. EPA latest $39 million "estimated" cost of
dredging the harbor. The City has provided
U.S. EPA with hundreds of examples of sites where capping has worked and been
approved by federal and state environmental agencies[7]
(including on the Fox River in
Just recently the
National Research Council, in a study funded by the U.S. EPA and the National
Academy of Sciences, concluded:
At sites where structures, debris, hardpan,
or bedrock limit dredging effectiveness, the desired cleanup levels, if based
on the attainment of specified chemical concentrations, are unlikely to be
met by dredging alone.[10]
(Emphasis Added)
Concern was also raised by a
Technical Review Committee that included the Illinois EPA about whether the
Now U.S. EPA is
suggesting that after the PCBs are ineffectively dredged, they should be
capped. Why bother with dredging the
PCBs in the first place if they will have to be capped? As U.S. EPA explains, an engineered cap is
dismissed from further consideration not for scientific, but for political and
bureaucratic reasons:
In
situ capping is not a viable option for the federally authorized navigation
channel segments of
Maybe there are
political reasons why consensus cannot be achieved to use the most reliable and
cost effective technology. Maybe the ACOE
will object to the placement of an "obstruction" (an engineered cap)
in the harbor. The ACOE may very well
object to an engineered cap even though, after more than twenty three years of
failed attempts at cleanup,[13]
it has warned that
However, U.S. EPA should not weigh in what is
essentially a political and local land use issue. The job of U.S. EPA is to focus the public on
the best scientific solutions to environmental problems. U.S. EPA should be candid and tell the public
that, despite political and bureaucratic constraints, capping is a more
reliable and cost effective solution than dredging. Whether an engineered cap is a viable
solution for the harbor is a scientific, not a political, question. The political debate concerning how to best
solve the problem of PCB contaminated sediments in the harbor should take place
with accurate and unbiased scientific information. Maintaining the harbor as a deep industrial harbor
should not be a predetermined outcome that censors honest and open scientific discussion. Perhaps unwittingly, this is exactly what U.S.
EPA has allowed to happen. The citizenry
deserves unbiased scientific information so that they, through their elected
representatives, may make informed policy decisions. Let the public decide whether it makes sense
to spend $39 million + on a remedy that may not work or whether a more cost
effective and reliable alternative, an engineered cap, should be
implemented. Our elected representatives
may need to cut through bureaucratic red tape in order to implement the most
sensible remedy for
[1] Budget estimate provided to the Yeoman Creek Landfill Steering Committee by the U.S. Army Corps of Engineers on June 11, 2003.
[2] "Waukegan won't allow harbor PCBs in dump", Chicago Tribune, April 16, 2004.
[3] No. 54, A Resolution Respecting the Dredging of Waukegan Harbor adopted by the Waukegan City Council on May 7, 2007. Since May 2007, U.S. EPA has further increased its estimate of total project costs, and the City's share of project costs, to $39 million and $13.7 million, respectively.
[4] "Waukegan rejects harbor cleanup agreement with EPA", U.S. EPA Press Release, August 22, 2007.
[5]
September
4, 2007 electronic mail from William Bow, environmental consultant to the
[6] The City provided the Illinois EPA and U.S. EPA on numerous occasions with information on the feasibility of In-Situ subaqueous capping of the PCB contaminated sediments, including, for example, a letter from LFR dated March 21, 2007.
[7] The City provided Illinois Environmental Protection Agency (Illinois EPA) and U.S. EPA with a copy of U.S. EPA's own summary of sediment capping projects.
[8] "EPA, WDNR propose change to Fox River cleanup plan", U.S. EPA Press Release, November 13, 2006.
[9] Letter from Doug Scott, Director of Illinois EPA, dated April 30, 2007.
[10] Sediment Dredging at Superfund Megasites: Assessing the Effectiveness, Committee on Sediment Dredging at Superfund Megasites, Board on Environmental Studies and Toxicology
Division on Earth and Life
Studies, National Research Council of the
[11] Technical Review Committee Comments on Waukegan Harbor Sediment Remediation dated February 21, 2007, Comment #10.
[12] "Evaluation the In-Situ Capping Option at Waukegan Harbor", prepared by U.S. EPA on April 25, 2007.
[13]
"Waukegan
Harbor, Illinois, Confined Dredged Disposal Facility", U.S. Army Corps of
Engineers, Chicago District, April 1984 (report discusses 15 possible locations
for the disposal of PCB contaminated sediments in
[14]
"Waukegan
Harbor Cleanup: Our Final Opportunity", selected slides from Army Corps of
Engineers PowerPoint presentation to the
[15]
Great
Lakes Recreational Boating, dated March 2007, prepared by the Army Corps of
Engineers, p. 78 ("[